Stainless steel wire ball valve installation precautions

Release time: 2018-09-18
Stainless steel wire ball valve installation precautions:
(1) Remove the protective cover on both sides of the flange end and rinse it with the valve fully open.
(2) Before installation, the whole machine test should be carried out according to the specified signal (electric or pneumatic) (to prevent the use of vibration due to transportation). After passing the test, it can be installed on the line (wiring according to the electric actuator circuit diagram).
(3) Before preparing to connect to the pipeline, the remaining impurities in the pipeline must be flushed and removed (these materials may damage the seat and the ball).
(4) During installation, do not use the actuator part of the valve as a lifting point for lifting to avoid damage to the actuator and accessories.
(5) This type of valve should be installed in the horizontal or vertical direction of the pipe.
(6) The pipe near the installation point should not be drooped or subjected to external force. Pipe supports or supports can be used to eliminate the deviation of the pipeline.
(7) After connecting with the pipe, cross-tighten the flange connection bolt with the specified torque.